A5.com Announces New Data Center Progress

This month marks the half-way point in our project to complete our new Tier3 datacenter at 303 E. Washington in Bloomington, Il With an anticipated opening date of December 15, 2012, the aggressive pursuit has gone flawlessly. We’ve seen substantial progress including deployment of major HVAC and electrical systems, new walls and office space, and a new secure equipment yard for our mechanical systems. We now also have confirmation that (4) telecommunications companies will be deploying initially including Frontier Communications, US Signal, Stratus Networks, and Coretec. We have talked to a number of others including CIRBN, Comcast, and Windstream about potential deployments and look forward to helping solve your DR and cloud challenges! We hope to be completely moved in by December, 2012 at this pace.